150
Participants
Start Date
November 1, 2023
Primary Completion Date
December 31, 2025
Study Completion Date
December 31, 2025
tdcs lDLPFC
The current is 2mA, duration is 1200s, fade in 30s, fade out 30s, anode is on the F3, cathode is on the FP2.
tdcs rVLPFC
The current is 2mA, duration is 1200s, fade in 30s, fade out 30s, anode is on the F6, cathode is on the FP1.
Sham
The current only persist in the fisrt 30s, duration is 1200s, fade in 30s, fade out 30s, anode is on the F3/F6, cathode is on the FP2/1.
RECRUITING
Guangzhou Brain hospital(Guangzhou Huiai Hospital), Guangzhou
Guangzhou Psychiatric Hospital
OTHER_GOV